PrepAway - Latest Free Exam Questions & Answers

Which of the following is an acceptable method for handling positive project risk?

Which of the following is an acceptable method for handling positive project risk?

PrepAway - Latest Free Exam Questions & Answers

A.
Exploit

B.
Avoid

C.
Mitigate

D.
Transfer

Explanation:

Exploit is a method for handling positive project risk.
not the positive risk.


Leave a Reply