PrepAway - Latest Free Exam Questions & Answers

Which of the following tasks you would do in reaction to risk event occurrence?

You are the project manager of GHT project. A risk event has occurred in your project and you
have identified it. Which of the following tasks you would do in reaction to risk event occurrence?
Each correct answer represents a part of the solution. Choose three.

PrepAway - Latest Free Exam Questions & Answers

A.
Monitor risk

B.
Maintain and initiate incident response plans

C.
Update risk register

D.
Communicate lessons learned from risk events

Explanation:

When the risk events occur then following tasks have to done to react to it:
Maintain incident response plans
Monitor risk
Initiate incident response
Communicate lessons learned from risk events
Answer C is incorrect. Risk register is updated after applying appropriate risk response and at the
time of risk event occurrence.


Leave a Reply