PrepAway - Latest Free Exam Questions & Answers

What term is given to this newly created risk event?

Marie has identified a risk event in her project that needs a mitigation response. Her response
actually creates a new risk event that must now be analyzed and planned for. What term is given
to this newly created risk event?

PrepAway - Latest Free Exam Questions & Answers

A.
Residual risk

B.
Secondary risk

C.
Infinitive risk

D.
Populated risk

Explanation:

Secondary risks are the risks that come about as a result of implementing a risk response. This
new risk event must be recorded, analyzed, and planned for management.
Answer A is incorrect. A residual risk event is similar to a secondary risk, but is often small in
probability and impact, so it may just be accepted.
Answer D is incorrect. Populated risk event is not a valid project management term.
Answer C is incorrect. Infinitive risk is not a valid project management term.