What approach can you use to achieve this goal of improving the project’s performance through risk analy

You work as a project manager for BlueWell Inc. Management has asked you to work with the key
project stakeholder to analyze the risk events you have identified in the project. They would like
you to analyze the project risks with a goal of improving the project’s performance as a whole.
What approach can you use to achieve this goal of improving the project’s performance through
risk analysis with your project stakeholders?

PrepAway - Latest Free Exam Questions & Answers

A.
Involve subject matter experts in the risk analysis activities

B.
Involve the stakeholders for risk identification only in the phases where the project directly
affects them

C.
Use qualitative risk analysis to quickly assess the probability and impact of risk events

D.
Focus on the high-priority risks through qualitative risk analysis

Explanation:

By focusing on the high-priority of risk events through qualitative risk analysis you can improve the
project’s performance.
Qualitative analysis is the definition of risk factors in terms of high/medium/low or a numeric scale
(1 to 10). Hence it determines the nature of risk on a relative scale.
Some of the qualitative methods of risk analysis are:
Scenario analysis- This is a forward-looking process that can reflect risk for a given point in time.
Risk Control Self -assessment (RCSA) – RCSA is used by enterprises (like banks) for the
identification and evaluation of operational risk exposure. It is a logical first step and assumes that
business owners and managers are closest to the issues and have the most expertise as to the
source of the risk. RCSA is a constructive process in compelling business owners to contemplate,
and then explain, the issues at hand with the added benefit of increasing their accountability.
Answer A is incorrect. Subject matter experts can help the qualitative risk assessment, but by
focusing on high-priority risks the project’s performance can improve by addressing these risk
events.
Answer B is incorrect. Stakeholders should be involved throughout the project as situations within
the project demand their input to risk identification and analysis.
Answer C is incorrect. Qualitative analysis does use a fast approach of analyzing project risks, but
it’s not the best answer for this