PrepAway - Latest Free Exam Questions & Answers

Which one of the following is NOT an input to the risk identification process?

You are the project manager of the GHY project for your organization. You are working with your
project team to begin identifying risks for the project. As part of your preparation for identifying the
risks within the project you will need eleven inputs for the process. Which one of the following is
NOT an input to the risk identification process?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality management plan

B.
Stakeholder register

C.
Cost management plan

D.
Procurement management plan

Explanation:

The procurement management plan is not one of the eleven inputs for the risk identification
process. The eleven inputs to this process are:
risk management plan, activity cost estimates, activity duration estimates, scope baseline,
stakeholder register, cost management plan, schedule management plan, quality management
plan, project documents, enterprise environmental factors, and organizational process assets.


Leave a Reply