PrepAway - Latest Free Exam Questions & Answers

What will be your immediate action?

You are the project manager of a large networking project. During the execution phase the
customer requests for a change in the existing project plan. What will be your immediate action?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the risk register.

B.
Ask for a formal change request.

C.
Ignore the request as the project is in the execution phase.

D.
Refuse the change request.

Explanation:

Whenever the customer or key stakeholder asks for a change in the existing plan, you should ask
him/her to submit a formal change request. Change requests may modify project policies or
procedures, project scope, project cost or budget, project schedule, or project quality.
a change is requested in the project.


Leave a Reply