You are the program manager for your organization and you are working with Alice, a project
manager in her program. Alice calls you and insists you to add a change to program scope. You
agree for that the change. What must Alice do to move forward with her change request?

PrepAway - Latest Free Exam Questions & Answers

A.
Add the change to the program scope herself, as she is a project manager

B.
Create a change request charter justifying the change request

C.
Document the change request in a change request form.

D.
Add the change request to the scope and complete integrated change control

Explanation:

Change requests must be documented to be considered. Alice should create a change request
form and follow the procedures of the change control system.