What should be considered while developing obscure risk scenarios?

What should be considered while developing obscure risk scenarios?
Each correct answer represents a part of the solution. Choose two.

PrepAway - Latest Free Exam Questions & Answers

A.
Visibility

B.
Controls

C.
Assessment methods

D.
Recognition

Explanation:

The enterprise must consider risk that has not yet occurred and should develop scenarios around
unlikely, obscure or non-historical events.
Such scenarios can be developed by considering two things:
Visibility
Recognition
For the fulfillment of this task enterprise must:
Be in a position that it can observe anything going wrong
Have the capability to recognize an observed event as something wrong