PrepAway - Latest Free Exam Questions & Answers

Which of the following inputs will be needed for the qualitative risk analysis process in your project?

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to
begin the qualitative risk analysis process. Which of the following inputs will be needed for the
qualitative risk analysis process in your project?
Each correct answer represents a complete solution. Choose all that apply.

PrepAway - Latest Free Exam Questions & Answers

A.
Project scope statement

B.
Cost management plan

C.
Risk register

D.
Organizational process assets

Explanation:

The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical
response. The inputs to the Qualitative Risk
Analysis process are:
Organizational process assets
Project Scope Statement
Risk Management Plan
Risk Register
Answer B is incorrect. The cost management plan is the input to the perform quantitative risk
analysis process.


Leave a Reply