What this resulting risk is known as?

You are the project manager of HGT project. You have identified project risks and applied
appropriate response for its mitigation. You noticed a risk generated as a result of applying

response. What this resulting risk is known as?

PrepAway - Latest Free Exam Questions & Answers

A.
Pure risk

B.
Secondary risk

C.
Response risk

D.
High risk

Explanation:

Secondary risk is a risk that is generated as the result of risk response.
Answer A is incorrect. A pure risk is a risk that has only a negative effect on the project. Pure risks
are activities that are dangerous to complete and manage such as construction, electrical work, or
manufacturing.
result of risk response.