PrepAway - Latest Free Exam Questions & Answers

What type of risk response is this?

Judy has identified a risk event in her project that will have a high probability and a high impact.
Based on the requirements of the project, Judy has asked to change the project scope to remove
the associated requirement and the associated risk. What type of risk response is this?

PrepAway - Latest Free Exam Questions & Answers

A.
Exploit

B.
Not a risk response, but a change request

C.
Avoidance

D.
Transference

Explanation:

Risk avoidance involves changing the project management plan to eliminate the threat entirely.
The project manager may also isolate the project objectives from the risk’s impact or change the
objective that is in jeopardy. Examples of this include extending the schedule, changing the
strategy, or reducing the scope. The most radical avoidance strategy is to shut down the project
entirely. Some risks that arise early in the project can be avoided by clarifying requirements,
obtaining information, improving communication, or acquiring expertise.
Answer A is incorrect. Exploit risk response is used for positive risk or opportunity, not for negative
risk.
Answer D is incorrect. Transference allows the risk to be transferred, not removed from the
project, to a third party. Transference usually requires a contractual relationship with the third
party.
Answer B is incorrect. This risk response does require a change request, in some instances, but
it’s the avoidance risk response and not just a change request.


Leave a Reply