You are the project manager of the NGQQ Project for your company. To help you communicate
project status to your stakeholders, you are going to create a stakeholder register. All of the
following information should be included in the stakeholder register except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Stakeholder management strategy

B.
Assessment information of the stakeholders’ major requirements, expectations, and potential
influence

C.
Identification information for each stakeholder

D.
Stakeholder classification of their role in the project

Explanation:

The stakeholder management strategy is generally not included in the stakeholder registry
because it may contain sensitive information that should not be shared with project team members
or certain other individuals that could see the stakeholder register. The stakeholder register is a
project management document that contains a list of the stakeholders associated with the project.
It assesses how they are involved in the project and identifies what role they play in the
organization. The information in this document can be very perceptive and is meant for limited
exchange only. It also contains relevant information about the stakeholders, such as their
requirements, expectations, and influence on the project.
Stakeholder classification should be included in the stakeholder register.