PrepAway - Latest Free Exam Questions & Answers

which of the following?

Risks with low ratings of probability and impact are included for future monitoring in which of the
following?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk alarm

B.
Observation list

C.
Watch-list

D.
Risk register

Explanation:

Watch-list contains risks with low rating of probability and impact. This list is useful for future
monitoring of low risk factors.
Answer D is incorrect. Risk register is a document that contains the results of the qualitative risk
analysis, quantitative risk analysis, and risk response planning. Description, category, cause,
probability of occurring, impact on objectives, proposed responses, owner, and the current status

of all identified risks are put in the risk register.
during risk identification process.