Which of the following MOST specifically defines the procedures to follow when scheduled system patching
fails resulting in system outages?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Risk transference
B.
Change management
C.
Configuration management
D.
Access control revalidation
Explanation:
Change Management is a risk mitigation approach and refers to the structured approach that is followed to
secure a company’s assets. In this case ‘scheduled system patching’.