PrepAway - Latest Free Exam Questions & Answers

Why would the Project Manager escalate an issue to the Project Board?

Why would the Project Manager escalate an issue to the Project Board?

PrepAway - Latest Free Exam Questions & Answers

A.
The Project Board is responsible for determining the priority of all issues

B.
Direction is required on the best response for preventing the issue from occurring

C.
The issue is forecast to cause a deviation beyond stage tolerance and advice is required

D.
Escalating issues is a means of providing the Project Board with a regular update on
their status

Explanation:


Leave a Reply