Which task is performed by the Change Authority?

Which task is performed by the Change Authority?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the configuration management system when a change is approved

B.
Set a change budget

C.
Approve or reject a request for change within approved limits

D.
Refer changes that exceed budgetary limits to the Project Manager for approval