Which product summarizes progress and is used to decide whether to amend the project
scope or stop the project?
A.
End Stage Report
B.
End Project Report
C.
Checkpoint Report
D.
Product Status Account
You must be logged in to post a comment.
The answer A is right, Managing Successful Projects With PRINCE2, Section A.9.1