Identify the missing word(s) in the following sentence. Quality assurance provides
assurance to the [?] that the project is being conducted appropriately whilst Project
Assurance provides the same assurance to all the project’s stakeholders.
A.
Project Manager
B.
Supplier groups
C.
Executive
D.
corporate or programme management organization
Answer D is right. Managing Successful Projects, table 6.1.