Which is NOT an objective of the Controlling a Stage process?

Which is NOT an objective of the Controlling a Stage process?

PrepAway - Latest Free Exam Questions & Answers

A.
Coordinate the delivery of products as agreed in the Stage Plan

B.
Update the Business Case with any changes agreed with the Project Board

C.
Implement actions to control the impact of risks that occur during the stage

D.
Review the Business Case at regular intervals to assess the impact of changes that
occur during the stage

Explanation: