Which products, identified when creating a product breakdown structure, should each have
a corresponding entry in the Risk Register?
A.
Those that have been broken down into sub-products
B.
Those to be created outside the scope of the project
C.
Those that have been completed, but have NOT been quality checked
D.
Those dependent on more than one other product
Explanation: