Which process is used by a Team Manager to coordinate work on one or more of the project’s products?

Which process is used by a Team Manager to coordinate work on one or more of the
project’s products?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiating a Project

B.
Controlling a Stage

C.
Managing a Stage Boundary

D.
Managing Product Delivery