Which statement about the Directing a Project process is FALSE?

Which statement about the Directing a Project process is FALSE?

PrepAway - Latest Free Exam Questions & Answers

A.
Supports the PRINCE2 principle of manage by exception

B.
Is triggered by a request to initiate a project

C.
Covers the day-to-day activities of the Project Manager

D.
Provides a mechanism for the Project Board to assure that there is continued business
justification