PrepAway - Latest Free Exam Questions & Answers

Tag: Exam PRINCE2-FOUNDATION

Exam PRINCE2-FOUNDATION: PRINCE2 Foundation

Which of the following statements about lines of authority and reporting are true?

Which of the following statements about lines of authority and reporting are true? 1. The
Project Manager has day-to-day control for a management stage within the limits laid, 2. If a
Team Manager forecasts a deviation beyond Work Package tolerances, this should be
referred to the Project Manager down by the Project Board.

Which of the following statements about the Project Initiation Documentation are true?

Which of the following statements about the Project Initiation Documentation are true? 1.
The Project Initiation Documentation is used to ensure that a sound basis exists. 2. The
Project Initiation Documentation should be updated at the end of each stage to reflect the
current status of a project before the Project Board authorizes a project,


Page 1 of 2412345...1020...Last »