When should the Project Board refer to corporate or programme management for a decision?

When should the Project Board refer to corporate or programme management for a
decision?

PrepAway - Latest Free Exam Questions & Answers

A.
The stage requires resources

B.
It is forecast that project level tolerance will be exceeded

C.
The Senior Supplier or Senior User needs to be changed

D.
Any request for change needs to be approved