What process is used by the Project Manager to maintain focus on delivery of a stage’s products within a

What process is used by the Project Manager to maintain focus on delivery of a stage’s
products within agreed tolerances?

PrepAway - Latest Free Exam Questions & Answers

A.
Managing Product Delivery

B.
Managing a Stage Boundary

C.
Directing a Project

D.
Controlling a Stage

8 Comments on “What process is used by the Project Manager to maintain focus on delivery of a stage’s products within a

    1. benjamin says:

      All answers show green, so the site does not provide the answer. However it can’t be answer d, since controlling a stage is not to maintain delivery within tolerance. Controlling a stage is about taking corrective action.

      The answer is product delivery, which obejective (page 185) is : “The planned products are delivered to expectations and within tolerance.”




      0



      0
  1. Mohankumar says:

    The right answer is D, Managing Successful Projects With PRINCE2, Section 15.2

    The question specifically mentions ‘Used by Project Manager’ hence ‘Controlling the Stage is the process and the last point under Section 15.2 – Objective clarifies this.




    1



    0
  2. Ashu says:

    The right answer is A,”The objective of the Managing Product Delivery process is to ensure that:
    The planned products are delivered to expectations and within tolerance