Which is NOT included in the PRINCE2 definition of a project?

Which is NOT included in the PRINCE2 definition of a project?

PrepAway - Latest Free Exam Questions & Answers

A.
A project is a temporary organization

B.
A project’s purpose is to deliver one or more business products

C.
A project is part of business as usual’

D.
A project is based on an agreed Business Case