Which describes a risk event?

Which describes a risk event?

PrepAway - Latest Free Exam Questions & Answers

A.
The derivation or sources of a potential risk to the project

B.
The achievement of a milestone on the Project Plan

C.
The area of uncertainty in terms of the threat or opportunity

D.
The sequence of events and actions that will be put in place if a risk occurs

Explanation: