Which describes risk impact?

Which describes risk impact?

PrepAway - Latest Free Exam Questions & Answers

A.
How likely the risk is to occur in a given project situation

B.
The effect of the risk on the delivery of project objectives

C.
Timeframe within which the risk might occur

D.
The trigger that occurred giving rise to the risk