PrepAway - Latest Free Exam Questions & Answers

What product records any time tolerances agreed between the Project Manager and Team Manager?

What product records any time tolerances agreed between the Project Manager and Team
Manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Work Package

B.
Project Initiation Documentation

C.
Product Description

D.
Stage Plan

Explanation:


Leave a Reply