Which does the Executive need to ensure is in place before the project is initiated?

Which does the Executive need to ensure is in place before the project is initiated?

PrepAway - Latest Free Exam Questions & Answers

A.
The Project Initiation Documentation is complete

B.
The Project Plan has been approved

C.
All Work Packages are authorized

D.
An understanding of how the project will contribute to corporate objectives