At an agreed frequency, a Team Manager will send a [ ?

Identify the missing words in the following sentence. At an agreed frequency, a Team
Manager will send a [ ? ] to the Project Manager.

PrepAway - Latest Free Exam Questions & Answers

A.
Highlight Report

B.
Product Status Account

C.
Checkpoint Report

D.
Work Package