What process is used by the Project Board to respond to an Exception Report?

What process is used by the Project Board to respond to an Exception Report?

PrepAway - Latest Free Exam Questions & Answers

A.
Controlling a Stage

B.
Managing a Stage Boundary

C.
Managing Product Delivery

D.
Directing a Project