Which should be funded from a change budget?

Which should be funded from a change budget?

PrepAway - Latest Free Exam Questions & Answers

A.
The Starting up a Project process

B.
A fallback plan

C.
An agreed change to the scope of a project

D.
A change to a plan, within allocated tolerances, due to poor estimating

Explanation: