Why does PRINCE2 recommend three different levels of plans?

Why does PRINCE2 recommend three different levels of plans?

PrepAway - Latest Free Exam Questions & Answers

A.
To cover initiation, specialist work and exception situations

B.
To match the different aspects of the product-based planning technique

C.
To provide appropriate detail to each of the different levels of management within the
project

D.
As an allowance for initiation, product delivery and project closure