Why does PRINCE2 recommend three different levels of plans?
A.
To cover initiation, specialist work and exception situations
B.
To match the different aspects of the product-based planning technique
C.
To provide appropriate detail to each of the different levels of management within the
project
D.
As an allowance for initiation, product delivery and project closure