If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?

If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager
report?

PrepAway - Latest Free Exam Questions & Answers

A.
Corporate management

B.
Project Board

C.
Project Assurance

D.
Project Manager