Which is a purpose of the Closing a Project process?

Which is a purpose of the Closing a Project process?

PrepAway - Latest Free Exam Questions & Answers

A.
Delegate day-to-day management of the end of the project to the Project Manager

B.
Authorize the final stage of the project

C.
Confirm that all benefits defined in the Business Case have been achieved

D.
Recognize whether objectives set out in the original Project Initiation Documentation
have been achieved