PrepAway - Latest Free Exam Questions & Answers

You need to update your project budget so that Project will automatically calculate future costs without requi

You are managing a project in Microsoft Office Project Standard 2007. The cost of a resource has increased. The resource is assigned to a task that is currently in progress. You need to update your project budget so that Project will automatically calculate future costs without requiring manual adjustments. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the resources standard rate in the Resource Sheet.

B.
Update the resources Actual Cost in the Resource Usage view.

C.
In the resources Cost table, set the standard rate to increase on the effective date of the cost increase.

D.
Create a resource with the new rate and assign that resource to all tasks starting on or after the effective date of the cost increase.


Leave a Reply