Which view should you use?

You are assigning resources to a project in Microsoft Office Project Standard 2007. You allocate generic resources to a task and apply a work contour to some of the assignments. You need to view the assignments to verify that the work has been distributed correctly. Which view should you use?

PrepAway - Latest Free Exam Questions & Answers

A.
Network Diagram

B.
Resource Graph

C.
Resource Sheet

D.
Task Usage