You need to enter data into the project plan to recalculate the task finish date

You are tracking a project in Microsoft Office Project Standard 2007 by both duration and work effort. The work on a fixed units task is not proceeding as scheduled. You have data for the last status period from the resource assigned to the task. You need to enter data into the project plan to recalculate the task finish date. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Change the task type to effort-driven.

B.
Update the Actual Work and Remaining Work data.

C.
Change the task type to Fixed Duration, and then update the Remaining Work data.

D.
Change the task type to Fixed Duration, and then update the Actual Work and Remaining Work data.