You are creating a project schedule in Microsoft Office Project Standard 2007. You set the project start date to today and enter a task. You notice that the year shown in the project timescale does not match the date shown in the date field. You need the timescale to show the current year instead of the next year. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Modify the project calendar.

B.
Use the starting year for fiscal year numbering.

C.
Set new tasks to start by default on the current date.

D.
Set the label for the timescale year tier to Year 1, Year 2 & (From Start).