You need to update the task

You are tracking a project in Microsoft Office Project Standard 2007. A resource is assigned to a task that currently has a duration of 20 days. The resource informs you that she has worked on the task for 5 days, and will complete it in another 10 days. You need to update the task. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the Work and Actual Start fields for the assignment in the Task Usage view.

B.
Update the % Complete and Remaining Duration fields for the task in the Tracking Gantt view.

C.
Update the Physical % Complete and Remaining Duration fields for the task in the Gantt Chart view.

D.
Update the Budget Work and Units fields for the assignment in the Gantt Chart view with the task form displayed.