PrepAway - Latest Free Exam Questions & Answers

You need to calculate the number of resources necessary to complete the task in the required time

You are creating a project plan in Microsoft Office Project Standard 2007. A task in your plan has a fixed duration of 10 days. You have an estimate of how many hours of work the task will require. You need to calculate the number of resources necessary to complete the task in the required time.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the assignment units equal to the task duration.

B.
Set the assignment units equal to the estimated hours of work.

C.
Set the task duration equal to the estimated hours of work, and then view the resource histogram.

D.
Assign one resource to the task, enter the estimated hours of work, and then view the assignment units in the Gantt Chart view.


Leave a Reply