PrepAway - Latest Free Exam Questions & Answers

You need to update the status date in the project schedule to ensure the correct calculation of your projects

In Microsoft Office Project Standard 2007, you are monitoring the progress lines and earned value of your project. You need to update the status date in the project schedule to ensure the correct calculation of your projects progress. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Enter the appropriate status date in the Project Information dialog box.

B.
Enter the appropriate status date in the project files Properties dialog box.

C.
Modify settings so that Project calculates progress lines based on the project status date.

D.
Modify settings so that Project propagates changes made to the task completion status to the project status date.


Leave a Reply