You need to modify the project to reflect this temporary change

You are managing a project schedule in Microsoft Office Project Standard 2007. Two resources are changing from the day shift to the night shift for 2 weeks. You need to modify the project to reflect this temporary change. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the Night Shift calendar as the project calendar.

B.
Apply the Night Shift calendar to each resource’s calendar.

C.
Add a Night Shift entry to the exceptions of the project calendar, with the appropriate dates and hours set for these 2 weeks.

D.
Add a Night Shift entry to the exceptions of each resource’s calendar, with the appropriate dates and hours set for these 2 weeks.