How should you assign the resources?

You are developing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units, effort-driven task that has a duration of 10 days. You will assign two resources to the task. Each resource works 8 hours per day. You need to divide the 160 hours of effort evenly between the resources. How should you assign the resources?

PrepAway - Latest Free Exam Questions & Answers

A.
Individually, accepting the default values.

B.
Individually, entering a Units value of 50%.

C.
Simultaneously, accepting the default values.

D.
Simultaneously, entering a Units value of 50%.