PrepAway - Latest Free Exam Questions & Answers

You need to set up the schedule to work around this resource’s non-standard availability

Your organization has a 5-day work week, with working hours from 8:00 A M. to 5:00 P.M. On a project that you track in Microsoft Office Project Standard 2007, a resource works different days on alternate weeks: Monday, Tuesday, and Friday in Week 1 and only Monday and Tuesday in Week 2. Each task on your schedule has a duration of at least 2 weeks. You need to set up the schedule to work around this resource’s non-standard availability. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set up two resources that use different calendars, and then assign them to the tasks by week.

B.
Set up two exceptions to the projects Standard calendar, one for each weeks pattern. Set the recurrence of both to alternate weeks.

C.
Set up two exceptions to the resources Standard calendar, one for each weeks pattern. Set the recurrence of both to alternate weeks.

D.
Set up two calendars for the resource, each set to the working pattern for either Week 1 or Week
2. Then assign the resource to tasks by using either of the calendars.


Leave a Reply