PrepAway - Latest Free Exam Questions & Answers

You need to model the relationship between these tasks

You are creating a schedule in Microsoft Office Project Standard 2007. A project phase represented by Summary Task B should finish at the same time as Task A . You need to model the relationship between these tasks. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a start-to-finish dependency from Task A to Summary Task B.

B.
Create a finish-to-finish dependency from Task A to Summary Task B.

C.
Create a finish-to-finish dependency from Summary Task B to Task A.

D.
Create a finish-to-finish dependency from Task A to the final task of Summary Task B.


Leave a Reply