PrepAway - Latest Free Exam Questions & Answers

You need to schedule the task

You are adding a task to an existing project schedule in Microsoft Office Project Standard 2007. The task should start Tuesday, January 5 and must complete by Friday, January 8. You need to schedule the task. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set a Must Start On constraint on January 5.

B.
Set a Finish No Later Than constraint on January 8.

C.
Set a Must Start On constraint on January 5 and a Finish No Later Than constraint on January 8.

D.
Set a Start No Earlier Than constraint on January 5 and a Finish No Later Than constraint on January 8.


Leave a Reply