PrepAway - Latest Free Exam Questions & Answers

You need to ensure that when you update schedule information, Project does not schedule work in the past

You are updating a project schedule in Microsoft Office Project Standard 2007. A task with one resource assigned to it was scheduled to be completed before the current status date. You update the % Complete field according to the status provided by the resource. The remaining portion of the work is still scheduled in the past. You need to ensure that when you update schedule information, Project does not schedule work in the past. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the progress lines at the status date.

B.
Set the current status date in the project information.

C.
Set the calculation option to Move end of completed parts after status date back to status date.

D.
Set the calculation option to Move start of remaining parts before status date forward to status date.


Leave a Reply