You need to save the new template without including completed work data from the existing project

Using Microsoft Office Project Standard 2007, you are creating a project template from an existing project. You need to save the new template without including completed work data from the existing project. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Save the project as a template, selecting only the Actual Values option.

B.
Save the project as a template, selecting only the Values of all baselines option.

C.
Clear the baseline and then save the file as a template, using the default settings.

D.
Delete the values in the Duration column and then save the file as a template, using the default settings.